Note: The reference to “DAY” refers to a day in which work is carried out and does not imply sequential “calendar days”. There are certainly weekends, holidays, rain days, unexpected delays, etc. through the course of construction. The “DAY” is a time estimate for reference as to how long the specified tasks may take to complete. This Timeline displays all items in a complete build out and includes items that are not components of a 7 Day Aframes Home Kit such as electrical, plumbing, sheetrock, etc.
“A” Trusses & Roof Panels - - A, B & C
“A” Trusses & Roof Panels - C, D & E + Fascia Boards
Final screw down of Roof Panels & Tape Seams + Rear Wall
Front Wall + Sheathing on Front & Rear Walls
Roof Sheathing + Metal
Roof Sheathing + Metal ⏲️ House is now dried inand the initial main components of the 7 Day Aframe Kit are assembled -
Siding & Plumbing Rough-in + Top out
Siding & Plumbing Rough-in + Top out
Electric Rough-in
Electric Rough-in
Inspections
Sheetrock + Painting Exterior Siding
Sheetrock + Painting Ext. Siding
Sheetrock + Painting Ext. Siding + Decks
Sheetrock + Decks
Painting Sheetrock
Painting Sheetrock + HVAC Inside Install
Interior Trim & Cabinets
Interior Trim & Cabinets
Interior Trim & Cabinets
Flooring
Flooring
Countertops & Outside Unit Install
Plumbing Trim Out
Plumbing Trim Out + Electric Trim Out
Inspections + Exterior Door Paint
Cabinet & Door Hardware + Stairs
Punch List
Punch List
Punch List
Punch List
Final Inspections